New Radnor Middle School

Click here for pictures!

 

 

July 2007

The Radnor Middle School project has been underway for more than 75 weeks. Less than 50 weeks remain to reach the scheduled completion date of June 1, 2008. As of May 29, 2007, the project was ahead of schedule in most areas.

Current manpower averages 50.

Interior construction:

Classroom wing:

The ceiling grids, tiles and painting on the first through fourth floors are complete, with chalk- and tack boards installed on the second through fourth floors. Flooring – VCT and carpeting – is complete on floors 2 through 4; installation on the first floor has begun. Installation of lockers follows the flooring installation, with many lockers already in place.

Casework on all floors is 99-percent complete – fully installed in the science rooms and the library.

Light fixtures on all floors are installed, as are ductwork and insulation. The teledata communications wiring and cables are completed.

The heat pumps on the fourth floor are operational, and the first through third floors are following.

Cafeteria:

Installation of kitchen quarry tile and cafeteria/corridor terrazzo is complete. The food service equipment is installed; the final connections will be complete by the end of July.

Gymnasium:

Painting (with non-VOC paints) is complete. The installation of basketball backstops is ongoing.

What still needs to be done?

The flooring in both gymnasiums is being planned, wood in the main gym and poured rubber flooring in the auxiliary gym.

Highlights of the interior:

Technology Center – The Technology Center is complete, with books already being moved in. Some of the exciting features include the five-panel wall for the RMS Mural Project, the full glass wall filling the space with light, the Zodiac brand natural reception counter and the wonderful and comfortable furnishings for students.

Auditorium – Interior walls are being finished and sound system cabling is being installed.

Lighting – State-of-the-art T-5 lighting with full-spectrum-color renditioning is being installed throughout the facility.

Heating/cooling – The geothermal heating and cooling system is complete and heat pumps are isolated from instructional areas to reduce unwanted noise.

The various computer labs are wired for data.

Exterior construction:

The exterior face block and brick are 99 percent complete. Work is ongoing on curbing, sidewalks and the parking lot on Louella and Windermere avenues.

The canopy at the new bus loop is well underway and is slated to be finished by the end of July.

The shingle roofing is complete. The vegetative roof, which will help moderate temperature and manage rainwater runoff, is installed in two places. The geothermal heating and cooling units are installed.

The bus loop is being constructed, including parking areas adjacent to the administration building which will have groundwater-recharge systems installed beneath. New curbing and sidewalks are being completed around the entire administration building.

What still needs to be done?

The parking lots and playing fields are slated to be finished by the winter/spring. Site lighting fixtures and school zone flashers are currently being installed as areas are finished.

Highlights of the exterior:

Geothermal wells – All 144 wells are completed and the piping to the building has been completed.

Green roof – Two large portions of the vegetated roof have been completed and the balance are being installed.

Rain garden – two areas outside the Windermere side of the building and within the student entry courtyard will be planted with indigenous plants that will be able to absorb substantial amounts of water. Underneath is a groundwater-recharge system, which will absorb the excess.

Parking update:

The Louella/Windermere parking area should be completed prior to the opening of the building in September, followed by the South Wayne parking area after removal of the existing building in the winter/spring seasons.

Demolition of old RMS:

The demolition of the old bus loop canopy has begun, as has the asbestos abatement of the entire building. Demolition will begin in earnest in August and should be completed within approximately three months.

LEED/Green requirements:

The owner, architect and contractors continue to pursue a LEED silver-certified building and are aiming for gold, if possible – an upgrade from the original goal of silver.

One element of LEED includes the recycling of construction waste. The goal has been to recycle 75% of all waste produced during the construction process. To date, we have achieved 85% reduction of waste by weight going to land fills.

Current RMS grants and awards:

2006: $25,000 grant award from the Pa. State Public School Building Authority for High Performance Green School Planning

March 2007

 

The Radnor Middle School project has been underway for close to 60 weeks. About 70 weeks remain to reach the scheduled completion date of June 1, 2008. As of Jan. 22, 2007, the project was ahead of schedule in most areas.

 

Current manpower averages 100.

Interior construction:

The interior masonry walls in the classrooms are 99% complete. The installation of the wood windows in the classroom and assembly wings is 85% complete.

What still needs to be done?

The mechanical contractor has nearly completed the duct work in the classroom wing and is about 30% complete in the assembly wing. Heat pumps have been installed, and testing for the second, third and fourth-floor piping has begun.

 

The installation of light fixtures is ongoing, and plumbing fixtures have been installed in the classroom wing on the third and fourth floors.

 

Sprinklers are installed on the second, third and fourth floors, and work has begun on the first floor.

 

The teledata communications contractor has completed the wiring for data/communications and speaker cables on the second, third and fourth floors.

Highlights of the interior:

Library – Planning for the raised floor distribution network for HVAC and data is underway and furnishings have been ordered for delivery this spring.

Auditorium – Interior walls are being finished and sound system cabling is being installed.

Lighting – State-of-the-art T-5 lighting with full-spectrum-color renditioning is being installed throughout the facility.

Heating/cooling – The geothermal heating and cooling system is being completed and heat pumps are isolated from instructional areas to reduce unwanted noise.

            The various computer labs are being wired for data.
            Life safety systems
(fire sprinklers, alarms and extinguishers) are being installed.

Exterior construction:

The steel erection and detailing is 98% complete, and the exterior face block and brick are 90% complete.

            What still needs to be done?

Work on the retaining wall at Louella and Windermere avenues is continuing. The shingle roofing contractor is currently 95% complete on the gym and auditorium roofs.

Highlights of the exterior:

Geothermal wells – All 144 wells are completed and the piping to the building has been completed. The school will have a geothermal heating and cooling system, using a series of 144 500-foot-deep wells transferring the thermal energy to and from the ground.

 

The system uses no fossil fuels and has no harmful greenhouse gas emissions. It will be coupled to heat recovery systems that will extract typically wasted heat from exhaust air prior to leaving the building. The incoming air will be dehumidified, as well as filtrated using high efficiency air filters.

 

This system, combined with the use of low volatile organic compounds throughout the building, will provide the best of air quality for the learning environment.


Green roof
– Two large portions of the vegetated roof have been completed and the balance will be installed this spring.

 

The vegetated roof systems installed on the flat roofs will provide for evapotransporation and a reduced heat island effect from the roof of the new building.

 

The 3" organic material, combined with the sedum growth medium, will provide oxygen back into the atmosphere and should lengthen the life of the roof underneath. It will help in storm water management by using some of the rainfall for growth, while cooling the building from the sun's rays.

 

Bus loop update:

The bus loop will begin to be reconstructed in May and all bus traffic will be routed off of Windermere Avenue until the end of this school year.

Parking update:

Parking continues to require everyone’s patience. The Louella parking area should be completed prior to the opening of the building in September, followed by the South Wayne parking area after removal of the existing building.

Demolition of old RMS:

Plans are being prepared for the demolition of the existing building this fall. Elements of the existing building are being removed for inclusion in the new facility.

 

LEED/Green requirements:

The owner, architect and contractors continue to pursue a LEED silver-certified building and are aiming for gold, if possible.

 

One element of LEED includes the recycling of construction waste. The goal has been to recycle 75% of all waste produced during the construction process. To date, we have achieved 85% reduction of waste by weight going to land fills.

 

Current RMS grants and awards:

2006: $25,000 grant award from the Pa. State Public School Building Authority for High Performance Green School Planning

 

September 13, 2006

Current manpower for the Radnor Middle School Project is averaging 99. As construction activities continue with increased masonry work and closing in the building, this number will most likely rise.

The masonry contractor is in the process of installing the CMU on the exterior of the building and is continuing masonry walls. The interior masonry walls in the classroom section for floors 1, 2 and 3 are currently 99 percent complete and floor 4 is 22 percent complete. Exterior installation of ground face block at the classroom section has begun.

The steel erection and detailing is currently 98 percent complete. All material for steel erection is on site.

Concrete floor slabs are proceeding as areas become available; currently floor slabs are 95 percent complete. The mechanical, plumbing and electrical contractors are continuing their rough ins. The electrical contractor is in the process of installing conduit in CMU walls and overhead areas. The installation of sleeves in decking and under slab work has been completed. The transformer manhole for the primary electrical service has been completed; the underground in the mechanical room and relocation of the primary service for the administration building has been completed as well. The plumbing contractor is in the process of installing pipe hangers in the classroom section and assembly wing as well as in-wall plumbing. The installation of underground pipe has been completed. The mechanical contractor is continuing duct/sheet metal hanger installation. The roof curb installation at the classroom section is complete.

The site work contractor is proceeding with backfill of foundation s and installation of sanitary sewer lines. Sanitary sewer and installation of gas lines around the administration have been completed as well as the temporary bus loop around the administration building.

Geothermal well drilling has commenced there are a total of 144 wells with 44 left to drill. There are currently three drill rigs in operation. Underground geotechnical piping at the mechanical room has been completed.

The current updated schedule reflects the project as being ahead of schedule in most areas. We are currently focused on the exterior masonry veneer and assembly wing roof.

 

 

 

 

Sample of the new facade.


For a photo timeline of demolition of the middle school activity center click HERE

 


The new Radnor Middle School will allow Radnor School District to continue its tradition of educational excellence. Targeted to open in the fall of 2007, the new Radnor Middle School will be constructed to accommodate 1,000 students in grades 6, 7 & 8. The cost of construction is estimated at $37.9 million, with total project costs estimated at approximately $48 million.

The building will consist of a four-story instructional wing and an open lobby connecting the wing to large group spaces. The grounds will provide for a full-sized football/soccer field and combination soccer/field hockey/lacrosse field. It will also include a full-sized softball diamond.

The Middle School Building Project Committee researched architecture that would help mirror and support the philosophy of middle level education. They also looked for design concepts that were ecologically and environmentally friendly. The architect and engineers were directed to build this school using "green" building principles — with strict attention to building materials, construction methods, and design of the mechanical systems. The architects and engineers will also incorporate recycled materials or materials derived from managed resources into the project.

In addition to the environmental, ecological and energy efficient systems and features for the new building, the new school will also include small learning communities for students at each grade level. Each of those learning communities contains a center core space where the whole group can gather for special programs and for integrated learning experiences. The District is committed to building a school that best serves the interests of our students, their parents, our staff, and our community as we move ahead in the 21st century.

 

SITE PLANS/DRAWINGS/ARCHITECTURAL RENDERINGS:

July 2005 Site Plan Link

Blackney Hayes 3-Dimensional Renderings of Radnor Middle School Project

                Drawing 1       Drawing 2        Drawing 3

                Drawing 4       Drawing 5        Drawing 6                                                      

LEED Certification
Projected Borrowing Capacity
Traffic:
Water Studies/Information:
Carnegie Model

Educational Specifications

 
 

 

 

 

 

   

Home | Departments | Curriculum | Schools | School Board | Publications | Links | Contact | Job Opportunities | Staff Access

© 2006, Radnor Township School District | 135 S. Wayne Avenue, Wayne, PA 19087 | (610) 688-8100 | radnor@rtsd.org