Building The New Ithan Elementary School

At its June 28, 2022 regularly scheduled Board Business Meeting the Radnor Township School Board approved the Administration’s recommendation to replace Ithan Elementary School on the current grounds based on a thorough feasibility study and community feedback.  

The long-term feasibility study found areas of concern at Ithan Elementary School that needed to be addressed immediately. Administration presented a preliminary timeline for replacing Ithan Elementary School which included stages for planning, development and construction to take place over a 4-to-6-year period. At their November 29, 2022 Board Business Meeting, the Radnor Township School Board approved the selection of Breslin Ridyard Fadero Architects for design and bidding of the Ithan Elementary School Project.  

A Steering Committee of parents, community members, staff, School Board members, and architects generally meets the last week of each month to guide the project. 

Ithan Elementary School New Construction Project

New IES Project Update: September 2025

During September we saw construction of a new temporary playground at IES as well as clearing and removal of trees. 

New IES Project Update: August 2025

Demolition has begun on the new Ithan Elementary School project. 

New IES Project Update: May 2023

The New Ithan Elementary School Steering Committee Members took time in April to tour local newly built schools for research and inspiration.

New IES Project Update: January 2025

The New Ithan Elementary School color renderings of various areas around the school.

Conceptual Schematic Design

See a conceptual schematic design of the proposed New Ithan Elementary School through this video rendering. 

1/17/24 Community Meeting

On Wednesday, January 17 at 4:30 p.m. in the IES cafeteria, our team gave an update on the New Ithan Elementary School project, including a presentation of the Design Development. This event was open to the public.

Anticipated for completion for the 2028-29 school year, the New Ithan Elementary Project addresses issues of outdated mechanical, electrical and plumbing systems, ADA non-compliance, and security concerns among other areas of critical concern.

The New Ithan Elementary Project is currently scheduled for completion for the 2028-29 school year. Below is a tentative timeline for various aspects of the project. Please note these dates may change and this webpage will be updated to reflect any changes. (Updated September 8, 2025)

  • Building Review
    • Determine location, size, and function of the new building.
    • Completed: May 2023
  • Schematic Design Phase
    • Meet with internal stakeholders and develop floor plan.
    • Completed: October 2023
  • Design Development Phase
    • A more detailed design to include technology integration,  input from teachers and administrators, educational space design, 3D space layouts.
    • Estimated completion: Spring 2024
  • Construction Document Phase
    • Completed: Spring 2025
  • Land Development
    • Estimated completion: Winter 2025
  • Bidding
    • Estimated completion: Fall 2025
  • Award of Contracts
    • Estimated completion: Spring 2026
  • Construction
    • Estimated Start: Spring 2026
    • Substantial Completion Spring of the 2027-28 School Year 
  • Final Completion:
    • Winter of 2028